Kenilworth station progress update – October 2016

Progress update: In recent weeks works have continued on site with the weigh bridge at the site entrance being removed. The perimeter fencing works has been started and is on-going. East side clearance works have taken place. The Severn Trent Water sewer diversion works contractor has been procured and approved.

kenilworthprogresssite1kenilworthprogressbarrierkenilworthprogresssite2
Works over the next four weeks will include;

The Severn Trent Water sewer diversion works which are required to construct the new station building will be starting. This will include some piling works.

The public right of way footbridge is due to be closed in the coming weeks. Updates will be given on the Kenilworth Rail Station website and notice board.

We will continue to provide monthly updates, to let you know how works are progressing. Should you have any comments or any questions associated with the Kenilworth Station project please contact Warwickshire County Council on: kenilworthstation@warwickshire.gov.uk