Kenilworth Rail Station Update – December 2016

The detailed design is complete with design reviews and approvals on going.

  • Construction is ongoing of the piling platform on the west side of the LSC2 railway line. Sectional flight auger piles will be installed to support the new platform and station building.
  • Kenilowrth station train

  • Site Clearance works on east side of the LSC2 line railway line have commenced.
  • ken-station-image-2

  • Severn Trent Water sewer diversion works to enable the construction of the new station building to be completed in January.
  • ken-station-image-3

  • Construction of a new manhole chamber on the Severn Trent Water sewer to be diverted.
  • ken-station-image-4

    Network Rail is carrying out some culvert survey works.

    Boundary fencing works are set to start in January.

    The public right of way will not be closing until the new year. Exact dates will be provided in a further update.