Kenilworth rail station update – February 2017

Works undertaken in January

Works have started on Platform 1 and on the station building.

50% of the concrete piles have been installed to enable this work to be done.

ken-station-1

The works to divert the Severn Trent sewer are ongoing. These works have been delayed by design approvals but are now 50% complete.

ken-station-2

Upcoming works

The Severn Trent sewer diversion will be completed.
Work to realign the Tanyard Stream at the east of the site will begin, diverting water away from the bridge.

ken-station-3

There will be overnight works at weekends over the course of February and March. All residents affected will receive a letter from the principal contractor.

The public right of way will close at the end of March. Further updates will be provided nearer the time.