Kenilworth Rail Station update – April 2017

The Tanyard stream diversion on the east of the site has been completed. The U-shape culvert units have been installed and the watercourse will be diverted into the new channel following the completion of the sealant works.

The piling for the proposed footbridge has been completed on the east side of the site.

The Severn Trent Water diversion is progressing, the tunnelling elements beneath the existing bridge and culvert have been completed.

Station platform and building piles on the west of the site are 50% complete and the foundations and pile caps have also been completed.